Seasons 4 – RTU Direct Replacement Time-lapse

Over one weekend, a new 172 ton Seasons 4 roof top unit (RTU) was installed in 5-story commercial office building located in Framingham, MA. The unit arrived onsite Friday night, September 11th, and was completely installed and commissioned by Sunday the 13th.  The 2-day timeline allowed for no impact to building tenants in the 162,000 sq. ft. office building. The unit has 172 tons in DX cooling capacity with 8 scroll compressors.  The total RTU weight is 32,300 lbs.  The Seasons 4 unit was supplied by Noble Associates, Inc.

The Seasons-4 unit alignment accounted for all of the old unit’s electric power, and control feeds, thereby eliminating the need for additional field conduit piping or wiring.

See the entire process above through a captured time-lapse!